Bridges #24N & #24S Replacement

ROCKINGHAM, Vt. — The following is a more detailed update of the construction to take place for the I-91 Rockingham Bridges #24N & 24S project over the Williams River for the week beginning Monday, Oct. 29.

I-91 northbound & southbound is reduced to one lane with no shoulders within the construction zone.

I-91 northbound motorists should be aware of merging ramp traffic entering the roadway!

Please use caution!

I-91 northbound bridge activities:

Monday through Thursday — 5 p.m. to 5 a.m.

Monday through Friday — daytime:

Continue work on both approaches. Continue curing of the concrete deck placements. Continue placement of the barrier curb.