The following is a more detailed update of the construction to take place for the I-91 Rockingham Bridges #24N & 24S project over the Williams River for the week beginning Monday, November 12, 2018.
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
I-91 northbound bridge activities:
Monday thru Thursday – 5 p.m. to 5 a.m.
Monday thru Friday – 7 a.m. to 5 p.m.
Continue work on both bridge approaches.
Continue placement of the concrete barriers on the bridge.
Website Updates Follow us on Facebook
Follow us on Twitter (#91rockbridges)
Live Traffic Camera
Call Stephanie Barrett with any questions or concerns regarding this project at
802-862-6085 or 866-602-6868.